21/06/2024
Happy News! The 2nd Phase of Reconstruction is finally complete!
West Baraboo Pavement markings were painted this morning! All of West Baraboo and the side roads Mulberry, Walnut, Connie, Cedar, Willow and Hill are open. On Highway 33 there will be soft close at Hill Street. This is for local Access to Prevail Bank, Westwood Park, Domino's, Jimmy John, AT&T and the homes along this section. There will be a hard closer just east of the Domino's/Jimmy Johns driveway.
As long as there are no delays on Monday, June 24th construction is expected to start in our 3rd phase segment from the eastern limit of Jimmy John’s / Domino’s driveway all the way to West Street. A-1 Excavating will need to go to West Street as this is the lower end of the sanitary sewer. Highway 33 will be completely closed just east of the Domino’s/ Jimmy Johns Driveway through West Street. In the beginning Draper, Summit, and West Streets will be closed. Park, Wood, and Center Streets will be open for cross traffic. Once they get through West Street they will open up from cross traffic and close Wood and Center streets for underground work.
The segment east of Domino's/Jimmy Johns driveway to Park St will be finished before school starts in the fall. The eastern limits of Park St - the eastern limits of Broadway St is still expected to be completed in November.
We would like to Thank you ALL for the patience and understanding as Mother Nature has not always been on our side the last few months. Have a great Weekend!