Day 1 of Monitoring and Evaluation.
CDF Monitoring and Evaluation committee visited a number of project to inspect the status and also determine the value of money disbursed.
1. AP's camp at Bukhayo West, the project was started some years back and it's now 50% complete, there is plead to the committee to ensure the project is complete.
2. Mundika Boys Administration Block, the project is 90% complete, with some variations of ramp and tiling the administration block will be ready to be used.
3. Budokomi Secondary Laboratory, the committee inquired about the status of the project, it was determined the project is 60% complete, with additional fund the project will be complete.
4. Classroom at Khudiri Primary, this is an upcoming Primary school established in 2017, CDF purchased 1 acre of land for the school, and constructed 3 number of classrooms, there is also ongoing classroom which is 50% complete.
5. Buyende Primary School, the committee sought to know about 5 number of classrooms that were to be renovated,
6. Visit at Bulanda Complex.
The committee visited Bulanda primary where they inspected renovation of 3 classrooms, it was satisfied that the amount disbursed is what is seen in the ground.
They also visited Bulanda Secondary School where recently they had purchased land for the school.